The arches and deck of the new cycle bridge in Stad Deinze were assembled on 18, 19, 25 and 26 January 2025. The access ramps will follow in a few weeks so that this bridge over the Lys diversion canal will be accessible this summer.
Some figures:
➡️ 56-metre span
➡️ 6-metre-wide deck at the abutments and 3 metres wide in the middle
➡️ Highest point of the steel arch = 16 metres above the water
➡️ 7 metres clearance under the bridge at normal water level
A project led by De Vlaamse Waterweg nv with the support of the European Union.